S5 · Grid at the GSB/WMM interface, asphalt on top · Keep your asphalt

Keep your asphalt. Put the grid in the base and build thinner.

OC-LW 40 (OC-HD 40 for the heaviest traffic) laid at the GSB/WMM interface, aggregate-filled, with at least 100 mm of compacted WMM above it. The bituminous layers follow MoRTH and the client's specification: bituminous concrete, SMA, mastic asphalt, cold mix or a RAP mix. Nothing changes above the grid.

Get my free estimate   Download the flier (PDF) (opens in a new tab)   Installation at a glance (PDF) (opens in a new tab)

OC-LW 40 laid at the GSB/WMM interface and filled with the same aggregate; WMM, DBM and BC above it exactly as MoRTH specifies

Installed cost, indicative*Design-specific₹251/sq ft (₹2,700/m²) materials in a 10,000 m² example
Opens to trafficAs todayyour contractor's asphalt programme
Laying rate+1 shiftper 1,000 m² for the grid
Product, for procurementOC-LW 40₹51–64/sq ft (₹550–690/m²), ex-works; OC-HD 40 for the heaviest traffic
2.0×base modulus, CBR 5%
22–24%less bituminous thickness at 3.5 MSA (IIT Hyderabad example)
14%thinner pavement overall at 3.5 MSA
1 shiftper 1,000 m² added

Why it wins

  • The base gets twice as stiff. Modulus improvement factor 2.00 on a CBR 5% subgrade, 1.63 on CBR 10%, from large-scale tests at IIT Hyderabad.
  • So the layers get thinner. In the IIT Hyderabad design examples, checked in IITPAVE to IRC:37: 14% thinner overall at 3.5 MSA, with 22–24% less bituminous and 11% less granular; 80 mm thinner at 50 MSA on CBR 5%.
  • Nothing changes above the grid. Your contractor's asphalt scope, plant and crew stay the same; the grid adds one shift per 1,000 m².
  • Weak subgrades. Where the granular base would otherwise be thick, the grid does the work of the extra aggregate.

Where it fits

Campus, township and approach roads · parking · plant peripheral roads · weak subgrades where the base would otherwise be thick.

Build-up

S5 cross-section

Choose S5 when

  • The client or consultant keeps asphalt
  • A thinner base, or a weak subgrade (tested at subgrade CBR 5–10%)
  • The same asphalt contractor builds it

Not ideal when

  • Asphalt is not required: S1 or S2 usually costs less
  • Subgrade CBR outside 5–10% without engineering verification

What we need from you

  • Area: length × width, or m²
  • Location: city or a map pin
  • Heaviest vehicle and vehicles a day
  • Soil CBR if you have it, or the soil type
  • The finish you want
  • A site photo or layout drawing

Get my free estimate

Datasheet

Installed rangeApplication timeTest dataProductProduct price, for procurementReference
Design-specific; ₹251 / sq ft (₹2,700 / m²) materials in a 10,000 m² example; 14% below the conventional section*Contractor's schedule; grid adds one shift per 1,000 m²; asphalt opens as it always doesMIF 2.00 at CBR 5%, 1.63 at CBR 10%: IIT Hyderabad large-scale tank tests, October 2025 · presented at TGS2026, IISc Bengaluru, for publication by SpringerOC-LW 40 · OC-HD 40 for the heaviest traffic · 100% recycled PP₹51–64 / sq ft (₹550–690 / m²) OC-LW 40 · ₹84–107 / sq ft (₹900–1,150 / m²) OC-HD 40 by order size, ex-works · ex-GST · ex-freightOrxa Energies, Bengaluru campus road · IIT Hyderabad test sections

*Installed cost varies with local material availability, labour, transport, base design and site conditions; every site is priced from its own design. Product prices exclude GST (18%) and logistics.

On site

Installation at a glance

The six steps, what you need and when it opens, on one page. The installation guide comes by email on request; the SOP, the hold-point checklists and the method statement for your site come with your order. We train your contractor’s team: on site for up to 3 days for orders of 2,000 m² or more once the site is confirmed ready, online at no extra cost below that; on-site training is built into the product rate (one PO).

Download (PDF, 1 page) (opens in a new tab)

Test reports

Bureau Veritas and Stedrant load tests, GreenPro, patent 398992, IIT Hyderabad research. See Engineering.

Drainage and terrain

Designs are customised to geography, rainfall intensity and topography: sub-surface drains sized to the rainfall class, cross-sections for plain and steep terrain.

What would your road or yard cost on GridMats?

An indicative estimate in about a minute, free. Our engineers follow with the design and the bill of quantities against your conventional section; the method statement your contractor will follow comes with your order.

Get my free estimate   Talk to an engineer on WhatsApp (opens in a new tab)