S5 · Grid at the GSB/WMM interface, asphalt on top · Keep your asphalt

Keep your asphalt. Put the grid in the base, designed per site.

Keep your asphalt: OC-LW 40 goes in the GSB/WMM base, aggregate-filled, under at least 100 mm of WMM. Everything above follows MoRTH.

Get my free estimate   Download the flier (PDF) (opens in a new tab)   Installation at a glance (PDF) (opens in a new tab)

Orxa Energies, Bengaluru: the road edge, with the grid in the base under the asphalt

Installed cost, indicative*Design-specific₹251/sq ft (₹2,700/m²) materials in a 10,000 m² example
Opens to trafficAs todayyour contractor's asphalt programme
Laying rate+1 shiftper 1,000 m² for the grid
Product, for procurementOC-LW 40₹51–64/sq ft (₹550–690/m²), ex-works; OC-HD 40 for the heaviest traffic
2.0×base modulus, CBR 5%
22–24%less bituminous thickness at 3.5 MSA (IIT Hyderabad example)
14%thinner pavement overall at 3.5 MSA
1 shiftper 1,000 m² added

Why it wins

  • The base gets twice as stiff. Modulus improvement factor 2.00 on a CBR 5% subgrade, 1.63 on CBR 10%, from large-scale tests at IIT Hyderabad.
  • So the layers get thinner. In the IIT Hyderabad design examples, checked in IITPAVE to IRC:37: 14% thinner overall at 3.5 MSA, with 22–24% less bituminous and 11% less granular; 80 mm thinner at 50 MSA on CBR 5%.
  • Your contractor's scope stays the same. The same asphalt scope, plant and crew, on the thinner layers of the GridMats design; the grid adds one shift per 1,000 m².
  • Weak subgrades. Where the granular base would otherwise be thick, the grid does the work of the extra aggregate.

Where it fits

Campus, township and approach roads · parking · plant peripheral roads · weak subgrades where the base would otherwise be thick.

Build-up

S5 cross-section

OC-LW 40 laid at the GSB/WMM interface and filled with the same aggregate; WMM, DBM and BC above it to MoRTH, at the thinner GridMats design thicknesses

OC-LW 40 (OC-HD 40 for the heaviest traffic) laid at the GSB/WMM interface, aggregate-filled, with at least 100 mm of compacted WMM above it, over a non-woven geotextile separation layer on the subgrade. The bituminous layers follow MoRTH and the client's specification: bituminous concrete, SMA, mastic asphalt, cold mix or a RAP mix. The same materials above the grid, at the thinner thicknesses of the GridMats design.

Choose S5 when

  • The client or consultant keeps asphalt
  • A thinner base, or a weak subgrade (tested at subgrade CBR 5–10%)
  • The same asphalt contractor builds it

Not ideal when

  • Asphalt is not required: S1 or S2 usually costs less
  • Subgrade CBR outside 5–10% without engineering verification

What we need from you

  • Area: length × width, or m²
  • Location: city or a map pin
  • Heaviest vehicle and vehicles a day
  • Soil CBR if you have it, or the soil type
  • The finish you want
  • A site photo or layout drawing

Get my free estimate

Datasheet

Installed rangeApplication timeTest dataProductProduct price, for procurementReference
Design-specific; ₹251 / sq ft (₹2,700 / m²) materials in a 10,000 m² example; 14% below the conventional section*Contractor's schedule; grid adds one shift per 1,000 m²; asphalt opens as it always doesMIF 2.00 at CBR 5%, 1.63 at CBR 10%: IIT Hyderabad large-scale tank tests, October 2025 · presented at TGS2026, IISc Bengaluru, for publication by SpringerOC-LW 40 · OC-HD 40 for the heaviest traffic · 100% recycled PP₹51–64 / sq ft (₹550–690 / m²) OC-LW 40 · ₹84–107 / sq ft (₹900–1,150 / m²) OC-HD 40 by order size, ex-works · ex-GST · ex-freightOrxa Energies, Bengaluru campus road · IIT Hyderabad test sections

*Installed cost varies with local material availability, labour, transport, base design and site conditions; every site is priced from its own design. The geotextile separation layer is a separate BoQ item, not included. Product prices exclude GST (18%) and logistics.

On site

All S5 photos on one page

Installation at a glance

The steps, what you need and when it opens, on one page. The installation guide comes by email on request; the SOP, the hold-point checklists and the method statement for your site come with your order. We train your contractor’s team: on site for up to 3 days for orders of 2,000 m² or more once the site is confirmed ready, online at no extra cost below that; on-site training is built into the product rate (one PO).

Download (PDF, 1 page) (opens in a new tab)

Test reports

Bureau Veritas and Stedrant load tests, GreenPro, patent 398992, IIT Hyderabad research. See Engineering.

Drainage and terrain

Designs are customised to geography, rainfall intensity and topography: sub-surface drains sized to the rainfall class, cross-sections for plain and steep terrain.

Defect liability

Defect liability: 1 year (DLP), our standard practice. After the training visit, your team shares project status updates (photographs, test reports, and any roadblocks or challenges) at each hold point and at the intervals set in the project agreement; the DLP applies only when these updates have been shared.

What would your road or yard cost on GridMats?

A free indicative estimate in about a minute. Our engineers follow with the design and the bill of quantities.

Get my free estimate   Talk to an engineer on WhatsApp (opens in a new tab)

Buying for several sites? One rate for 12 months: the annual rate contract →